Wicomico County. Maryland

Department of Public Works

 

Improvements Construction

Plan Review Checklist

Revised - Effective 5/1/06

 

Subdivision Name:_____________________    Location:___________________
 
Prepared By:__________________________    Date:______________________

 

  ~    if included or   N/A   if not applicable

 

A.               General Information

 

_____        1.     Plans prepared on 24’ x 36’ sheets

_____        2.     Index sheet showing entire subdivision and sheets numbered

_____        3.     Title which is descriptive, including section number

_____        4.     Tax map, parcel and grid

_____        5.     North arrow on each sheet

_____        6.     Plan view scale, min. 1” = 200’

_____        7.     Ownership and parcel number of adjacent properties

_____        8.     Street name, number and right-of-way width

_____        9.     Plan preparation and revision dates

_____        10.    Consultant’s name, address, telephone and fax

_____        11.    Owner’s name, address, telephone and fax

_____        12.    Vicinity map, min. scale 1” = 2000’

_____        13.    Subdivision area and disturbed area

_____        14.    On-site benchmark, NGVD (1929)

_____        15.    Legend for all symbols, both existing and proposed

_____        16.    Corporate limits

_____        17.    Name and location of bodies of water, tidal and non-tidal

_____        18.    Location and description of all utilities, i.e. water, sewer, stormwater, telephone, gas, electric and cable

_____        19.    Limits and description of all easements, i.e. access, drainage and utility

_____        20.    Standard county construction notes

_____        21.    Owner’s certification

_____        22.    Zoning district

_____        23.    Topography, both existing and proposed

_____        24.    Forest Conservation easements or exemption number

_____        25.    Critical areas limits, designation and buffers

_____        26.    Wetlands limits and buffers, tidal and non-tidal

_____        27.    Floodplain limits, zone and elevation

_____        28.    Floodway limits

_____        29.    Construction sequence, including pre-construction meeting

_____        30.    Limits of disturbed area

_____        31.    Construction specifications

_____        32.    Airport surface zone

_____        33.    Sediment control measures and notes, as approved by SCD

_____        34.    Historic District Limits

_____        35.    Public Drainage Association Limits

_____        36.    Agriculture Preservation District Limits

_____        37.    Paleo Channel Overlay District Limits

_____        38     Total number of proposed lots

_____        39.    Common areas labeled

_____        40.    Lot numbers and block letters

_____        41.    Proposed lot lines

_____        42.    Signed and sealed by Registered Professional Engineer or Land Surveyor

_____        43.    Cemetery location, including access

_____        44.    Bonding Estimate, 110% of estimated construction costs

_____        45.    Non-tidal wetlands disclaimer

_____        46.    Subdivision Construction Plan Review Fee, $2,000.00 + $20.00 per lot, payable to:  Wicomico County, Maryland

 

B.               Stormwater Management Design

 

_____        1.     Narrative summary of stormwater management analysis and data summary sheet

_____        2.     Tabular summary of pre- and post- development areas, curve numbers, times of concentration and flow rates

_____        3.     Drainage area map, min. scale 1” = 100’, showing:

                _____       a.     Sufficient topographic information to delineate watershed sub-areas, off-site if necessary

                        _____        b.     Hydrologic soil groups

                        _____        c.      Property boundaries

                        _____        d.     Time of concentration flow paths separated into overland, shallow concentrated and open channel flow

                        _____        e.     Land uses

_____        4.     Hydrologic calculations using SCS methodologies based on only the area being developed, TR-55 or TR-20

_____        5.     Peak runoff rate calculations for impervious areas only, use for routing if higher peak.

_____        6.     Water quality and quantity calculations, both required and provided

_____        7.     Planting plan and table

_____        8.     Forebay

_____        9.     Control structure and emergency spillway design, including anti-seep collars and anti-floatation

_____        10.    Ponds with side slopes steeper than 4:1, fenced by 6’ high security fencing with 12’ wide gate

_____        11.    Pond cross-sections showing bottom dimensions, side slopes and minimum 15’ wide accessible maintenance area

_____        12.    Trashrack

_____        13.    Maintenance schedule

_____        14.    Geotechnical analysis for infiltration facilities by Registered Professional Engineer, Geologist or Soil Scientist

_____        15.    Structural design of non-standard structures by Registered Professional Engineer

_____        16.    Standard details, i.e. endsections, rip-rap dissipators, riser & trash rack

_____        17.    Stormwater Management Plan Number, as assigned

_____        18.    Each facility labeled

_____        19.    Inspection and maintenance agreement with $40.00 recording fee, payable to:  Clerk of Circuit Court

 

C.               Storm Drainage Design

 

_____        1.     Drainage area map for drainage system showing similar information as stormwater management

_____        2.     Hydrologic calculations using rational method provided in tabular form, min. 10yr. storm

_____        3.     Structure and pipe schedules

_____        4.     Endsections and rip-rap on woven filter cloth

_____        5.     Minimum pipe cover, as recommended by manufacturer

_____        6.     Standard details, i.e. inlets, manholes & ditches

_____        7.     Plan and profile of pipes and ditches

_____        8.     Hydraulic gradient (25 year storm) and gutter spread calculations (2 year storm)

_____        9.     Structural design of non-standard structures by Registered Professional Engineer

_____        10.    Flow directional arrows

_____        11.    Pipe/ditch capacity and velocity

 

D.               Road Design

 

_____        1.     Road profile showing existing and proposed centerline grades, curb grades and vertical curve data

_____        2.     Road planview showing stationing, bearings, distances and horizontal curve data at centerline

_____        3.     Stations and elevations of all PC, PT, PRC, PVC, PVT and PVI points

_____        4.     Standard details, i.e. roads, curbs and valley gutters

_____        5.     Guard rail location

_____        6.     Road widening dedication

_____        7.     Existing and proposed right-of-way

_____        8.     Curb return radii

_____        9.     Handicap access ramp and sidewalk locations

_____        10.    State Highway Administration approval

_____        11.    Acceleration/Deceleration Lane

_____        12.    Road Construction Specifications with CBR Values

_____        13.    Traffic Control Plan

 

 

NOTE:    Refer to Wicomico County’s “Guidelines For Preparation Of Improvements Construction Plan” for more detail.